Name: Reilly, James Country: USA M/F: M Number of Flights: 3

Space Flights Launch Date - Shuttle Landing Date - Shuttle
1. STS-89 January 23, 1998 - Endeavour January 31, 1998 - Endeavour
2. STS-104 July 12, 2001 - Atlantis July 25, 2001 - Atlantis
3. STS-117 May 2007 - Atlantis May 2007 - Atlantis

Space Flights Descriptions
1. STS-89 Shuttle-Mir Docking Mission 8
Endeavour docked with Mir from January 24, 1998 to January 29, 1998.
2. STS-104 ISS Assembly Mission 7A - ISS Program Phase II is complete
Delivered the Quest Airlock on July 14, 2001 - Atlantis docked with the International Space Station (ISS) from July 14, 2001 to July 22, 2001.
3. STS-117 ISS Assembly Mission 13A (Scheduled)
Deliver the S3/S4 Truss Segments

Spacewalks - 3
Space Flights Date & Duration Purpose
STS-104 July 14, 2001 International Space Station Assembly - Prepare Quest Airlock for installation on Unity module. Connect wires between Quest and Unity
5 hours 59 minutes
STS-104 July 17, 2001 International Space Station Assembly - Attach two oxygen tanks and one nitrogen tank to Quest Airlock
6 hours 29 minutes
STS-104 July 20, 2001 International Space Station Assembly - First spacewalk from Quest Airlock. Attach second nitrogen tank to Quest airlock. Inspect gimbal assembly mechanism on P6 solar arrays and Floating Potential Probe
4 hours 2 minutes